Ballarat East Zone Substation

  • Project type
    COMMUNITY
  • Current stage
    PLANNING
  • Project duration
    2024 - 2026

Powercor is upgrading Ballarat’s energy network, ensuring all the city’s homes and businesses can access reliable and safe power as the region’s population grows. Zone substations help connect the higher voltage sub-transmission network to the lower voltage distribution network, allowing electricity to be distributed into our homes and businesses.

Ballarat currently has two substations, and a third is required to meet increasing demand and support the effective ongoing operation of bushfire safety devices installed in the region.

Project Outcomes

What is happening?

The Ballarat East substation will be located at 203 York Street on land owned by Powercor. This land has been zoned for use “for the construction of services and utilities” for more than 50 years.

Powercor has zone substations in the heart of residential communities in regions like Geelong, Warrnambool, Werribee, Sunshine, Melton, Laverton, Waurn Ponds and Torquay.

The Ballarat East substation will include an architecturally-designed exterior that will be co-designed with the local community. It will also feature technology that reduces the risk of powerline-related bushfires by instantly cutting power if a line is contacted.

Powercor is investing over $30 million to build the new zone substation. As part of the project, Powercor has developed a $2 million Community Benefits Package to provide benefits for individuals and the broader community. As part of this package, Powercor will establish a $200,000 Community Legacy Fund to support investments in parks, recreation or security within the community.

 

Why is this project important?

The Ballarat East Zone Substation will support Ballarat’s growing population, which is driving an increase in electricity demand on existing infrastructure.

It will support the growth in solar installations, electric vehicles and other electric equipment, and the network in the event of power outages and extreme weather.

The substation will also feature technology designed to protect the broader community by reducing the risk of powerline-related bushfires.

 

What’s next

Work to build Ballarat’s third zone substation is set to start in the week of 14 July, 2025.

We will keep local residents updated on our construction activities through monthly updates or on our website. If you have any questions, please email us at: majorprojects@powercor.com.au or call us at: 13 22 06

You can learn more about what to expect during construction here.

Bus stop temporary relocation

From first service Monday, 2 June to last service Monday, 30 June 2025. The Pennyweight Park/York Street Bus stop on Bus Route 20 (to Canadian) will be temporarily located 20 metres before the original bus stop.

While the zone substation is expected to be operating early 2026, activity on the site will continue until mid 2026 as we complete landscaping and other activities.

 

Fence design unveiled

After months of speaking with the community about what they would like the outside of the substation to look like, our architects have created a design that reflects that feedback and celebrates Ballarat’s rich history.

The fence will be painted in Pale Eucalypt (green) and Evening Haze (neutral), with some areas available for painted murals. It will feature modern perforated panels showcasing distinct patterns and pictures celebrating the local area. It will incorporate images of the gold rush era, the Eureka Stockade flag, some of Ballarat’s heritage buildings, Lake Wendouree and other local icons.

The fence will vary in height, from 3.1 to 3.5 metres, and will include soft low-level feature lighting to create a subtle effect at night. A range of native shrubs will be planted around the fence.

Image shown is an artist impression to visualise the concept. Final appearance may vary.

Image shown is an artist impression to visualise the concept. Final appearance may vary.

How to get involved

We are committed to working with the local community to design the new Ballarat Zone Substation and the nearby surrounds and invite you to play a pivotal role through our community co-design initiative.

Stage 2 community consultation now closed – next steps

Thank you to everyone who participated in Stage 2 of our community consultation. The survey is now closed and we appreciate your input on the final fence design, colour choices, feature lighting options and the Community Benefit Fund.

We are now in the evaluation stage, where we will review all feedback to finalise the design and determine the Community Benefit Fund outcome.

We’ll provide an update in 2025 on the outcomes and next steps.

Other ways to shape the project

If you would like to request a conversation with us personally you can call 13 22 06 during business hours or email majorprojects@powercor.com.au (external link).

You can also sign up to receive email updates on this project at Engage Powercor.

Webinar – EMF and water management

Thank you to everyone who attended our webinar on Wednesday 31 July. The recording is now available and can viewed at engage.powercor.com.au/ballarateastzss.

If you have any further questions or require assistance viewing the webinar recording please email majorprojects@powercor.com.au

Response to City of Ballarat

On 22 May 2024, the City of Ballarat Council moved a motion seeking an on-site visit between Powercor representative, councillors, council officers and residents in relation to the Ballarat East Zone Sub-Station project. Our response can be viewed here.

Property condition survey

As part of the construction of the new Ballarat East Zone Substation, Powercor is offering a complimentary property condition survey and report for properties within 50 metres of the construction site. This independent assessment records the current condition of eligible properties and serves as a reference in case any concerns arise during or after construction.

Community solar fund

We are offering payments up to $10,000 to fund the installation of 5kW solar systems or a battery for people whose homes (main dwelling) are materially within a 100-metre radius of the York Street site.

We’ve notified eligible residents about how to access our Community Solar Fund. We’ve released the payment process and provided an approved list of electrical contractors.

If you eligible for the payment but haven’t yet contacted us or received information, there is still time. For questions or for more information, email us at majorprojects@powercor.com.au or call 13 22 06.

 

 

Construction FAQs

What can the community expect during construction?

You can expect to see an increase in activity in the area. This will include more machinery, vehicles and workers moving on the York Street site and in the surrounding streets.

While the zone substation is expected to be operating by early 2026, activity on the site will continue until mid-2026 as we complete landscaping and other activities.

 

What type of work will occur on site?

There are five stages of work that will occur.

1) Benching and earthworks.

2) Foundations and major equipment Installation.

3) Pre-commissioning (equipment checks, testing)

4) Energisation and commissioning (turning it on)

5) Close out: Final tidy and follow up work

The first stage will involve preparing the site and conducting earthworks. This will lead to a noticeable change in the way the site looks.

 

How will construction progress in the first few weeks?

In the first 8 weeks, we will be setting up the site and completing earthworks. This includes preparing and levelling the ground. Activities will also involve the delivery and removal of ground materials including soil and rock.

We will also be installing site offices.

 

What equipment will you be using?

To complete this phase of works we will be using excavators, tipper trucks, rollers and other specialised machinery to move soil, compact surfaces and shape the site.

 

When will workers be on site?

Construction will occur during standard working hours, 7am to 6pm, Monday to Friday. There will be occasional work on weekends between 8am and 4pm.

 

How are you managing noise during construction?

To minimise noise impacts, construction will occur during standard working hours, 7am to 6pm, Monday to Friday, with occasional work on weekends between 8am and 4pm.

 

What measures are in place to control dust and dirt?

We are committed to reducing dust and dirt through a range of measures, including:

1) Regularly spraying water to reduce dust in dry conditions.

2) Where feasible covering exposed soil to help prevent dust from spreading.

3) Using a street sweeper as needed to keep nearby roads clear of dirt and debris.

 

How will environmental impacts be managed during construction?

Our crews will follow strict environmental guidelines to ensure the work is carried out safely. We have a dedicated environmental management plan in place for this project to minimise impacts on the surrounding area. This plan includes erosion and sediment controls to help protect the local waterway and we will responsibly manage waste and materials throughout the project.

 

How will local wildlife be protected during construction?

We are committed to protecting local wildlife and have measures in place to minimise any impact on native fauna. As part of our environmental management plan, we will assess the site for any habitats that may be affected and take steps to avoid disturbing them. If needed qualified specialists will assist in safely relocating wildlife.

 

Will there be any road or footpath closures?

Pedestrian access will be maintained. At times, we will need to close the access track next to the site for safety and access reasons.

If we need to temporarily change traffic and footpath access, we will provide advance notice and clear signage to guide residents safely around the worksite.

 

How will construction affect local parking and traffic?

You may notice more vehicles in the area while we complete our works but there will be no changes to traffic or parking. We aim to minimise disruptions and will communicate in advance if there are any temporary impacts near the worksite.

 

Who will be completing the work?

Our Powercor crews and authorised contractors will carry out the works. This includes experienced construction teams, machinery operators and specialist contractors. All personnel will follow strict safety and environmental management procedures to ensure the works are completed efficiently and with minimal disruption to the community.

 

How can residents stay informed about the project’s progress?

We will keep the community informed through:

1) Monthly updates detailing project milestones and upcoming activities.

2) Our website.

3) Direct communication channels for any questions or concerns.

For more information or to reach out to us:

Visit our website at: powercor.com.au/ballarateastzss

Email us at: majorprojects@powercor.com.au

Call us at: 13 22 06

Location of project

203 York Street, Ballarat East

Have a question?

Visit our Ballarat East Zone Substation project page on Engage Powercor to contribute to the design of the substation and sign up for email updates.

For all other enquiries, email us at majorprojects@powercor.com.au.

0

Important documents

Fact sheets

    Frequently asked questions

      Community notifications

        Other documents