CitiPower is installing new underground power cables to support growth in the Kew area and enable more capacity in the growing local network.
Works
CitiPower is continuing to install underground power cable connections along Charles Street, College Place, and Glenferrie Road in Kew. These works follow on from previous work in the area in late 2024.
What to expect
Current work schedule:
Works will take place on selected dates in February and March 2025.
Date | Time | Works |
Wed 05 Feb to Sat 08 Feb | 9am-3pm | Wall propping
Trenching |
Mon 10 Feb to Tues 11 Feb; Wed 12 Feb to Sat 15 Feb
Mon 10 Feb to Tues 11 Feb; Wed 12 Feb to Fri 14 Feb |
9am-3pm
9pm-5am |
Trenching
Excavation and boring |
Mon 17 Feb to Sat 22 Feb | 9am-3pm | Trenching |
Mon 24 Feb to Wed 26 Feb | 9am-3pm | Cable installation |
Thu 27 Feb | 9am-3pm | Cable jointing |
Fri 28 Feb | 9am-3pm | Commissioning of substation
Backfill |
Monday 3 Mar | 9am-3pm | Commissioning of LV cable |